Temporary buildings are well under way

The construction work on the temporary buildings is continuing on schedule.

All 186 separate sections are now in place and the contractor is in the process of fitting out the interiors of all the spaces. The external shells are situated, and power and data are being run into the classrooms as well as finishes like door frames.

It is amazing to think that from the start of work in June 2024 to the end of March 2025, two blocks of our school will be in place, complete with specialist science labs, art & design workshops, food technology rooms, computer suites and music and drama spaces. Each of these teaching spaces will allow us to continue to deliver our full balanced curriculum while the main build progresses.

We are now at a point that heads of department have visited the temporary accommodation, and give further feedback to the contractor (things like the number of plug sockets and their locations), and the facilities look very impressive. There will continue to be updates over the coming months, and it is hoped that we can share photographs after the Christmas holiday.